City Hall Rehabilitation Update

City Hall Rehabilitation Project Update from Engineer

December 2019
The Contractor has completed all drywall installation, including texturing of the sheetrock. The
electrical contractor has sent his submittals for review and should be ordering materials to begin
installation as soon as materials arrive. The Contractor will be providing the City with cost
estimates for flooring options as well as cost estimates to float, texture, and paint the interior
CMU blocks of the City Hall. We have finally resolved the electrical questions on the electrical
service and are in the process of obtaining a cost estimate for a generator for City Hall.